Fournisseur: VINCI Energies Transport et Transformation d’Energie

Un marché public archivé

Marchés publics récents dans lesquels le fournisseur VINCI Energies Transport et Transformation d’Energie est mentionné

2018-12-07   INELFE — Biscay Gulf — Electrical Interconnection FR-SP — Converter Stations (INELFE — INterconexión ELéctrica Francia-España)
The Biscay Gulf electrical interconnection consists of the construction of a 2 000 MW HVDC link. This link is composed of 2 (two) circuits rated 1 000 MW each at DC operating voltage of 400 kV, comprised of 4 power cables, 2 converter stations located close to 400 kV Cubnezais substation (France) and Gatica substation (Spain). The length of the route is estimated to be approx. 375 km long starting in Spanish Pais Vasco region (near Bilbao), with underground cable of about 15 km, a submarine section … Voir la passation de marché »
Fournisseurs mentionnés: CHANTIERS MODERNES NOUVELLE AQUITAINE HITACH ENERGY SWEDEN AB HITACHI ENERGY FRANCE HITACHI ENERGY SPAIN S.A.U, VINCI Energies España S.A.U VINCI Energies Transport et...