Ferme Eolienne Flottante de Groix & Belle-Ile (FEFGBI) Floating Offshore Windfarm — Supply and Installation of 66 kV Submarine and Undergound Power Cables
The purpose of this notice is to achieve: — 2 EPCI including the survey, design, engineering and compliance testing, procurement, manufacturing, construction, installation, burial and protection, completion, on-site testing, pre-commissioning, trial operation, spares provision and other services for: RTE's scope: underground export cable and accessories and optical fiber cable (only supply and assembly), landfall transition joint, submarine export cable (static and dynamic, optical fiber included) subsea accessories and associated equipments and services. FEFGBI's scope: inter-array dynamic cables, subsea accessories and associated equipments and services. — an Inspection Maintenance and Repair (IMR) contract for the RTE's scope, — an Inspection Maintenance and Repair (IMR) contract for the FEFGBI's scope.
Date limite
Le délai de réception des offres était de 2019-03-25.
L'appel d'offres a été publié le 2019-03-04.
Avis de marché (2019-03-04) Objet Champ d'application du marché
Titre: Travaux de construction de lignes électriques
Brève description:
The purpose of this notice is to achieve:
— 2 EPCI including the survey, design, engineering and compliance testing, procurement, manufacturing, construction, installation, burial and protection, completion, on-site testing, pre-commissioning, trial operation, spares provision and other services for:
RTE's scope: underground export cable and accessories and optical fiber cable (only supply and assembly), landfall transition joint, submarine export cable (static and dynamic, optical fiber included) subsea accessories and associated equipments and services.
FEFGBI's scope: inter-array dynamic cables, subsea accessories and associated equipments and services.
— an Inspection Maintenance and Repair (IMR) contract for the RTE's scope,
— an Inspection Maintenance and Repair (IMR) contract for the FEFGBI's scope.
— 2 EPCI including the survey, design, engineering and compliance testing, procurement, manufacturing, construction, installation, burial and protection, completion, on-site testing, pre-commissioning, trial operation, spares provision and other services for:
RTE's scope: underground export cable and accessories and optical fiber cable (only supply and assembly), landfall transition joint, submarine export cable (static and dynamic, optical fiber included) subsea accessories and associated equipments and services.
FEFGBI's scope: inter-array dynamic cables, subsea accessories and associated equipments and services.
— an Inspection Maintenance and Repair (IMR) contract for the RTE's scope,
— an Inspection Maintenance and Repair (IMR) contract for the FEFGBI's scope.
Référence Dates
Date d'envoi: 2019-03-04 📅
Date limite de soumission: 2019-03-25 📅
Date de publication: 2019-03-07 📅
Date de début: 2020-05-01 📅
Date de fin: 2027-12-31 📅
Identifiants
Numéro d'avis: 2019/S 047-108770
Numéro JO-S: 47
Informations complémentaires
If the applicant is a JV/consortium or a single company/group, the entity responsible for installing the submarine cable system as well as the entity responsible for manufacturing the submarine cable system (static and dynamic) will be expected to have a direct contractual relationship with RTE/FEFGBI.
If the applicant is a JV/consortium or a single company/group, the entity responsible for installing the submarine cable system as well as the entity responsible for manufacturing the submarine cable system (static and dynamic) will be expected to have a direct contractual relationship with RTE/FEFGBI.
Objet Champ d'application du marché
Brève description:
The purpose of this notice is to achieve:
— 2 EPCI including the survey, design, engineering and compliance testing, procurement, manufacturing, construction, installation, burial and protection, completion, on-site testing, pre-commissioning, trial operation, spares provision and other services for:
— 2 EPCI including the survey, design, engineering and compliance testing, procurement, manufacturing, construction, installation, burial and protection, completion, on-site testing, pre-commissioning, trial operation, spares provision and other services for:
RTE's scope: underground export cable and accessories and optical fiber cable (only supply and assembly), landfall transition joint, submarine export cable (static and dynamic, optical fiber included) subsea accessories and associated equipments and services.
RTE's scope: underground export cable and accessories and optical fiber cable (only supply and assembly), landfall transition joint, submarine export cable (static and dynamic, optical fiber included) subsea accessories and associated equipments and services.
FEFGBI's scope: inter-array dynamic cables, subsea accessories and associated equipments and services.
— an Inspection Maintenance and Repair (IMR) contract for the…
… RTE's scope,
… FEFGBI's scope.
This procurement process is led by both RTE and FEFGBI. RTE will be the employer and the owner of underground and submarine (static and dynamic) export cables (included associated equipments and services).
FEFGBI will be the employer and the owner of inter-array dynamic cables (included associated equipments and services).
Estimated quantities and associated works for cable supply and installation:
— 3 inter-array (dynamic) power cables (4 km in total) and associated equipments and services,
— 1 submarine (static and dynamic) export cable (28,8 km) and associated equipments and services,
— 1 underground export cable (4,5 km) and associated equipment and services (assembly) but excluding the civil work and cable laying,
— 1 underground optical fiber (4,5 km) and associated equipments and services (assembly) but excluding the civil work and cable laying.
Associated equipments and services include but are not limited to:
— landfall transition joint (including the joint pit),
— ancillaries equipments dedicated to underground export cable, including joints,
— electrical cable termination and jointing works,
— ancillaries equipments dedicated to submarine export cable and inter-array cables, especially their dynamic part such as bend stiffener, buoyancy modules, etc,
— power cable monitoring system.
All power cables and associated equipments detailed above shall be designed for a nominal voltage of 66 kV.
Description des options: If applicable, will be described in ITT documentation.
Nom du projet ou programme financé par l’UE: Project "FERME EOLIENNE FLOTTANTE DE GROIX & BELLE-ILE"
Informations complémentaires:
If the applicant is a JV/consortium or a single company/group, the entity responsible for installing the submarine cable system as well as the entity responsible for manufacturing the submarine cable system (static and dynamic) will be expected to have a direct contractual relationship with RTE/FEFGBI.
If the applicant is a JV/consortium or a single company/group, the entity responsible for installing the submarine cable system as well as the entity responsible for manufacturing the submarine cable system (static and dynamic) will be expected to have a direct contractual relationship with RTE/FEFGBI.
Lieu d'exécution
Site principal ou lieu d'exécution: Groix.
Informations juridiques, économiques, financières et techniques Conditions de participation
Habilitation à exercer l'activité professionnelle:
Information and formalities necessary to evaluate if the requirements are met are prescribed within the Pre-Qualification Questionnaire (PQQ). FEFGBI and RTE reserve the right to review it at any given point in time.
The PQQ is a questionnaire divided into general questions regarding the applicants and more specific questions regarding the applicants experience relevant to the scope of the project as well as health, safety and environment policies and organization. Full details about the PQQ process will be described within the PQQ documentation.
The PQQ is a questionnaire divided into general questions regarding the applicants and more specific questions regarding the applicants experience relevant to the scope of the project as well as health, safety and environment policies and organization. Full details about the PQQ process will be described within the PQQ documentation.
Situation économique et financière:
Information and formalities necessary to evaluate if the requirements are met are prescribed within the PQQ. FEFGBI and RTE reserve the right to review it at any given point in time.
Capacité technique et professionnelle:
Information and formalities necessary to evaluate if the requirements are met are prescribed within the PQQ. FEFGBI and RTE reserve the right to review it at any given point in time.
Exécution du marché
Dépôts et garanties exigés: If applicable, will be described in ITT documentation.
Principales conditions de financement et modalités de paiement et/ou référence aux dispositions pertinentes qui les régissent: If applicable, will be described in ITT documentation.
Forme juridique que devra revêtir le groupement d'opérateurs économiques attributaire du marché:
Applicants may submit bids as:
(i) single company/group or
(ii) a Joint Venture (JV)/consortium.
In the case of JV/consortium, PQQ responses will be accepted from applicants provided that at least 1 entity involved in the JV/consortium has registered interest before the closing date stated within the Contract Notice. All JV/consortium members will be required to sign non-disclosure agreements with FEFGBI and RTE.
Forme juridique que devra revêtir le groupement d'opérateurs économiques attributaire du marché
In the case of JV/consortium, PQQ responses will be accepted from applicants provided that at least 1 entity involved in the JV/consortium has registered interest before the closing date stated within the Contract Notice. All JV/consortium members will be required to sign non-disclosure agreements with FEFGBI and RTE.
PQQ responses will be required for all JV/Consortium members.
FEFGBI and RTE reserve the right to ask all the JV/consortium members to be jointly and severally liable in case of attribution.
An applicant who submits an offer as part of a JV/consortium shall not submit an offer as single/group company or with another JV/consortium.
An applicant who submits an offer as a single company/group shall not submit an offer as member of a JV/consortium.
Additional conditions may be added in the ITT documentation.
Procédure
Base juridique: 32014L0025
Droit des marchés publics applicable: French.
Nombre de candidats envisagé: 4
Heure limite de réception des offres: 15:00
Date d'envoi des invitations: 2019-06-01 📅
Langues dans lesquelles les offres ou les demandes de participation peuvent être présentées: anglais 🗣️
Période de validité de l'offre: 6 mois
Pouvoir adjudicateur Identité
Nom du pouvoir adjudicateur: FEFGBI — Ferme Eolienne Flottante de Groix & Belle-Ile
Adresse postale: 10 place de Catalogne
Commune postale: Paris
Code postal: 75014
Pays: Ile-de-France
🏙️ Contact
Point de contact: Arnaud Chantôme
Thibaud Astier
Courrier électronique: thibaud.astier@eolfi.com📧
URL des documents: https://rte-france.bravosolution.com/fr/login.html🌏
Référence Informations complémentaires
The different steps of this RFI are:
1) Applicants must request to participate to the PQQ process through the e-sourcing portal BravoSolution before the closing date detailed in section IV.2.2);
2) After expressing your interest in participating in this public notice on the BravoSolution portal and after the closure date of this public notice, an NDA will be issued and should be returned by the applicant within 2 working days of receipt;
3) Once the NDA is signed by the applicant, the PQQ will be sent out. The PQQ and subsequent ITT will be run through the "BravoSolution" portal.
RTE and FEFGBI reserves the right to exclude JV/consortium applicants who change the JV/consortium organisation through the process.
RTE and FEFGBI reserves the right to request from the applicant, at any time, evidence to the legal position of the JV/consortium.
Applicants should note that for certain aspects of the work (such as but not limited to underground cable supply and mounting), they may be required to select subcontractors from existing RTE qualification systems and/or to use pre-approved subcontractors. Details will be provided in the PQQ and/or ITT or during the tender process.
Applicants should note that for certain aspects of the work (such as but not limited to underground cable supply and mounting), they may be required to select subcontractors from existing RTE qualification systems and/or to use pre-approved subcontractors. Details will be provided in the PQQ and/or ITT or during the tender process.
Informations complémentaires Organe de révision
Nom: Tribunal de grande instance de Nanterre
Adresse postale: 179-191 avenue Joliot-Curie
Commune postale: Nanterre
Code postal: 92020
Pays: France 🇫🇷 Service auprès duquel des informations sur la procédure de recours peuvent être obtenues Identique à : Organe de révision
Source: OJS 2019/S 047-108770 (2019-03-04)