Partial replacement of the main line firefighting valves of the Service Tunnel associated with Viking Vohnson pipe coupers replacement

Eurotunnel

LOT 1 (Firm) : supply, delivery and installation of 1/3 existing valves + 15 % Viking Johnson pipe couplers
150 mm Diameter, Class 300, lugged firesafe metal seated butterfly valves with a WCB carbon steel body, ASTM A351 stainless steel disc EN 10088-3 stainless steel shaft and AISA 316 stainless steel seat with graphite packing, face to face dimension 70 mm, bare shaft. To suit existing Mastergear Type MZ / MZF operator gearboxes. All valves to come with material certs & to be warranted. To include all consumables to permit the installation Bolts & or nuts Washers joints etc.
Valves in 45 Cross Passage from a total of 135 Cross Passage. Exact location in Service Tunnel will be planned by Eurotunnel.
Design, supply & Installation of By-Pass system, Assembly, installation and testing of 150 mm dia valves with gearboxes and position indicators, Removal & installation & testing Viking Johnson pipe couplers
Replacement of existing firefighting valves in the Service Tunnel at the cross-passages.
To design & provide a temporary rolling By-Pass over a five cross-passage (5 CPs). Length of rolling by-pass Approximately 1.875 KM. This is to put in place to keep the fire system installation fully operational during the valves replacement process. The fire main supplies water in the event of an underground incident. This supply cannot be shut off for any reason what so ever, because of its in direct interface with the 4 “SAFE” stations (fire drenching & extinguishing stations in the running tunnels). The work sites are available & accessible 24 hr/7 days.
Access along Service Tunnel, through the work site, must be kept open, for emergency & maintenance vehicles during interventions on valves replacements, and bypass extensions.
Distance between 2 Cross Passage (access from Running Tunnel to Service Tunnel) of 375 m. 6 valves are concerned at each Southside CP (5 valves will be replaced with a new ones, one valve of those 6 will be removed and replaced by a spacer section only).
Valves in 45 CP are affected from a total of 135 CP. Exact location in Service Tunnel will be planned by Eurotunnel.
During the time that the valves are being exchanged the VJ Couplers on the linear line between CPs may be exchanged. Exact numbers and locations to be given by Eurotunnel.
Lot 2 (optional): - Optional supply, delivery & installation of 2/3 valves / 85 % Viking joints
Optional requirement: 67 % (for 90 Cross Passage)
Firefighting valves: for valves diameter 150 mm (qty: 495)
Closing spacers to be used for valves identified for removal but not replaced (qty : 90)
Supply
Optional requirement: for 85% of total quantity.
Viking joints (qty: circa 3625) Q-FIT 273 mm L.SLV
Installation of bypass system, valves gearboxes, Viking Johnson Couplers.
Optional requirement: for 67 % of total quantity.
By-pass line installation and roll on between work sites.
Assembly, installation and testing of 150 mm dia valves with gearboxes and position indicators.
Removal of old, installation & testing the required number of Viking Johnson joints.
Note the quantities could be adjusted according to economic or technical constraints

Date limite

Le délai de réception des offres était de 2014-06-10. L'appel d'offres a été publié le 2014-05-26.

Qui ? Qu'est-ce que c'est ? OĂą ?
Historique des marchés publics
Date Document
2014-05-26 Avis de marché
Avis de marché (2014-05-26)
Objet
Champ d'application du marché
Titre: Valves et tubes
Quantité ou étendue:
Lots 1Supply & installation— VALVES : 240 manuals Valves diameter 150 mm— VIKING JOINTS : 675 Viking Johnson pipe couplers diameter 150 mm.— BY PASS LINE : To an equivalent length of 5 interval between Cross passage ( 4-5 x 375 m) / QTY 1 only to supply for the all project / the same bypass line will be used to bypass cross passage section – to install and remove each time for new section.LOT 2Supply & Installation— VALVES: 480 valves diameter 150 mm— VIKING Johnson pipe couplers: 3625 Viking Johnson couplers diameter 150 mm Q-FIT 273 mm L.SLV.
Afficher plus
Métadonnées de l'avis
Langue originale: anglais 🗣️
Type de document: Avis de marché
Nature du marché: Services
Réglementation: Union européenne
Vocabulaire commun pour les marchés publics (CPV)
Code: Valves et tubes 📦

Procédure
Type de procédure: Procédure négociée
Type de soumission: Soumission pour tous les lots
Critères d'attribution
Offre la plus économique

Pouvoir adjudicateur
Identité
Pays: France 🇫🇷
Type de pouvoir adjudicateur: Service d'utilité publique
Nom du pouvoir adjudicateur: Eurotunnel
Adresse postale: Siege Exploitation BP 69
Code postal: 62904
Commune postale: Coquelles
Contact
Adresse Internet: http://www.eurotunnel.com 🌏
Courrier électronique: peggy.gouverneur@eurotunnel.com 📧
Téléphone: +33 321004328 📞

Référence
Dates
Date d'envoi: 2014-05-26 đź“…
Date limite de soumission: 2014-06-10 đź“…
Date de publication: 2014-05-28 đź“…
Identifiants
Numéro d'avis: 2014/S 102-179632
Numéro JO-S: 102
Informations complémentaires
Under the negociated procedure, Eurotunnel reserves the right to gradually reduce the number of competing bidders.

Objet
Champ d'application du marché
Catégorie de service: 1
Brève description:
LOT 1 (Firm) : supply, delivery and installation of 1/3 existing valves + 15 % Viking Johnson pipe couplers
150 mm Diameter, Class 300, lugged firesafe metal seated butterfly valves with a WCB carbon steel body, ASTM A351 stainless steel disc EN 10088-3 stainless steel shaft and AISA 316 stainless steel seat with graphite packing, face to face dimension 70 mm, bare shaft. To suit existing Mastergear Type MZ / MZF operator gearboxes. All valves to come with material certs & to be warranted. To include all consumables to permit the installation Bolts & or nuts Washers joints etc.
Afficher plus
Valves in 45 Cross Passage from a total of 135 Cross Passage. Exact location in Service Tunnel will be planned by Eurotunnel.
Design, supply & Installation of By-Pass system, Assembly, installation and testing of 150 mm dia valves with gearboxes and position indicators, Removal & installation & testing Viking Johnson pipe couplers
Replacement of existing firefighting valves in the Service Tunnel at the cross-passages.
To design & provide a temporary rolling By-Pass over a five cross-passage (5 CPs). Length of rolling by-pass Approximately 1.875 KM. This is to put in place to keep the fire system installation fully operational during the valves replacement process. The fire main supplies water in the event of an underground incident. This supply cannot be shut off for any reason what so ever, because of its in direct interface with the 4 “SAFE” stations (fire drenching & extinguishing stations in the running tunnels). The work sites are available & accessible 24 hr/7 days.
Afficher plus
Access along Service Tunnel, through the work site, must be kept open, for emergency & maintenance vehicles during interventions on valves replacements, and bypass extensions.
Distance between 2 Cross Passage (access from Running Tunnel to Service Tunnel) of 375 m. 6 valves are concerned at each Southside CP (5 valves will be replaced with a new ones, one valve of those 6 will be removed and replaced by a spacer section only).
Afficher plus
Valves in 45 CP are affected from a total of 135 CP. Exact location in Service Tunnel will be planned by Eurotunnel.
During the time that the valves are being exchanged the VJ Couplers on the linear line between CPs may be exchanged. Exact numbers and locations to be given by Eurotunnel.
Lot 2 (optional): - Optional supply, delivery & installation of 2/3 valves / 85 % Viking joints
Optional requirement: 67 % (for 90 Cross Passage)
Firefighting valves: for valves diameter 150 mm (qty: 495)
Closing spacers to be used for valves identified for removal but not replaced (qty : 90)
Supply
Optional requirement: for 85% of total quantity.
Viking joints (qty: circa 3625) Q-FIT 273 mm L.SLV
Installation of bypass system, valves gearboxes, Viking Johnson Couplers.
Optional requirement: for 67 % of total quantity.
By-pass line installation and roll on between work sites.
Assembly, installation and testing of 150 mm dia valves with gearboxes and position indicators.
Removal of old, installation & testing the required number of Viking Johnson joints.
Note the quantities could be adjusted according to economic or technical constraints
Numéro du lot: 1
Intitulé du lot: Supply and Installation - Firm Part
Brève description:
Firm requirement: for 33 % (for 45 Cross Passage)
Firefighting valves: for valves dia 150 mm (qty: 240)
Closing spacers to be used for valves identified for removal but not replaced (qty: 45)
Supply of Viking Johnson pipe couplers
Firm requirement: for 15 % of total quantity.
Viking Johnson joints (qty: 675) Q-FIT 273 mm L.SLV
Firm requirement: for 33 % of total quantity.
Design, supply and Installation of By-Pass system. Comprising 1 875 Km of Galvanised Alvenius 219 mm Victaulic pipes with couplers bends Tees valves & fittings suitable for duty up to 69 Bar. Desired Flow max 120 mÂł/hr at the drenching pump stations.
Afficher plus
Removal of old, installation & testing the required number of NEW Viking Johnson joints.
Numéro du lot: 2
Intitulé du lot: Supply and Installation - Optional Part
Brève description:
Optional requirement : 67 % (for 90 Cross Passage)
Firefighting valves: for valves diameter 150mm (qty: 495)
Optional requirement : for 85 % of total quantity.
Optional requirement: for 67% of total quantity.
Les variantes sont acceptées ✅
Quantité ou étendue:
Lots 1
Supply & installation
— VALVES : 240 manuals Valves diameter 150 mm
— VIKING JOINTS : 675 Viking Johnson pipe couplers diameter 150 mm.
— BY PASS LINE : To an equivalent length of 5 interval between Cross passage ( 4-5 x 375 m) / QTY 1 only to supply for the all project / the same bypass line will be used to bypass cross passage section – to install and remove each time for new section.
Afficher plus
LOT 2
Supply & Installation
— VALVES: 480 valves diameter 150 mm
— VIKING Johnson pipe couplers: 3625 Viking Johnson couplers diameter 150 mm Q-FIT 273 mm L.SLV.
Lieu d'exécution
Site principal ou lieu d'exécution: Eurotunnel concession all along the 50 Km of Service Tunnel.

Informations juridiques, économiques, financières et techniques
Conditions de participation
Habilitation à exercer l'activité professionnelle:
— Company registration certificate.
— Statement confirming no intention to file for bankruptcy.
— Statement confirming you are eligible to compete
— Statement confirming you have satisfied all social and fiscal obligations for last 2 years.
— Details of any court proceedings in last 5 years.
Situation économique et financière:
— Turn over an d results for the last 3 years
— Turn over and results for the last 3 years for above defined activity (see II.2.1)
— Details of any subsidiary company or parent company.
— Number of people employed / Number of people for each lot
— Certificates : Quality, Safety and Environment certification.
— Safety manual, frequency and seriousness rates of accidents in last 3 years
— Insurance certificate with amounts and risks warranted
Capacité technique et professionnelle:
— Relevant references in the respective domain of activity
— References for similar projects
— Description of the method followed in similar projects
— Equipment, material, people and ability to provide the services.
— References for each activity in terms of client, description, location, value.
— Copies of professional certificates, statements, and competences, (Quality, Environment etc)
— Workforce strength in the respective domain of activity
— Industrial and commercial profile of the Company
Exécution du marché
Dépôts et garanties exigés: Performance guarantee.
Principales conditions de financement et modalités de paiement et/ou référence aux dispositions pertinentes qui les régissent: Payment terms in 60 days from invoice date.
Forme juridique que devra revêtir le groupement d'opérateurs économiques attributaire du marché: Registered companies or groups of companies (partnership/JV).

Procédure
Langues
Langue: anglais 🗣️
français 🗣️

Pouvoir adjudicateur
Contact
Point de contact: Peggy Gouverneur
Adresse Internet: www.eurotunnel.com 🌏

Référence
Dates
Date de début: 2015-01-01 📅
Date de fin: 2015-12-31 đź“…
Date de début: 2016-07-01 📅
Date de fin: 2017-12-31 đź“…

Informations complémentaires
Organe de révision
Nom: Tribunal de Grande Instance de Lille
Commune postale: Lille
Code postal: 59034
Pays: France 🇫🇷
Téléphone: +33 320783333 📞
Fax: +33 320783452 đź“ 
Source: OJS 2014/S 102-179632 (2014-05-26)