One contract per lot: 1) UK 2731 (UK lot): DEL, DER and DEQ chillers for Hinckley point, England; 2) PE 2731 (French lot): DEL, DER and DEQ chillers for Penly, France

EDF SA - acting in its own name and in the name and on behalf of its affilited companies

The works currently identified include design, manufacturing and related services of the nuclear island chillers.
There are 8 to 10 chillers units per plant, from 300 to 3000 kW cooling power.
The scope of works for the proposed contract includes: studies, qualification, supply, manufacture, controls, factory tests, transport, erection, on site testings and commissioning for these equipment.